Estimated Cost |
Low Bid |
Firm |
Variance |
| Abatement |
$613,610 |
$884,000 |
First Capital Insulation |
$270,390 |
| Demolition |
$1,719,758 |
$1,360,000 |
Empire Wrecking |
-$359,758 |
| Fencing Barricades |
$73,758 |
|
C - |
-$73,758 |
| Façade Stabilization |
$2,888,000 |
$2,940,000 |
withdrawn |
$52,000 |
| General Conditions |
$464,662 |
included in General Trades Bid |
-$464,662 |
| Caissons |
$1,400,000 |
$1,085,000 |
Shelly Drilling |
-$315,000 |
| General Trades |
$10,490,767 |
$22,292,000 |
Wohlsen Construction |
$11,801,233 |
| Site & Utilities |
$1,795,464 |
$2,909,000 |
Horst Excavating |
$1,113,536 |
| Concrete |
$13,973,585 |
$16,200,000 |
Miller , Long & Arnold |
$2,226,415 |
| Precast Concrete |
$2,759,382 |
$2,554,500 |
High Construction |
-$204,882 |
| Masonry |
$1,371,330 |
$1,469,924 |
Johnson Masonry |
$98,594 |
| Steel |
$4,200,396 |
$7,886,000 |
Steel Fab Enterprises |
$3,685,604 |
| Roofing |
$1,297,044 |
$2,144,000 |
United States Roofing Corp. |
$846,956 |
| Glass & Glazing |
$2,165,926 |
$5,089,600 |
Hershocks, Inc. |
$2,923,674 |
| Drywall |
$6,145,678 |
$9,133,000 |
Novinger's, Inc. |
$2,987,322 |
| Painting |
$1,223,804 |
$1,724,500 |
M. Gordon & Son |
$500,696 |
| Food Service Hood |
$50,000 |
|
|
-$50,000 |
| Conveying System |
$2,351,980 |
$2,427,142 |
Schindler Elevator |
$75,162 |
| Plumbing |
$4,621,621 |
$4,444,444 |
W.G. Tomko, Inc. |
-$177,177 |
| Fire Protection |
$1,192,460 |
$1,197,800 |
King's Fire Protection |
$5,340 |
| HVAC |
$10,757,779 |
$10,969,000 |
Rado Enterprises |
$211,221 |
| Electrical |
$9,016,010 |
$8,757,000 |
Farfield Company |
-$259,010 |
| Telecom/AV |
$1,003,463 |
$664,856 |
Vistacom Audiovisual |
-$338,607 |
| Construction Management |
$2,790,000 |
$2,410,000 |
High Construction/Reynolds Construction |
-$380,000 |
| TOTAL BID ITEMS |
$84,366,477 |
$108,541,766 |
|
$24,175,289 |
| |
|
|
Over
Budget |
28.66% |